Brymark Installations Group was awarded numerous contracts to complete maintenance and upgrades on PCT’s Quadrant Ship Loader.
Brymark’s scope of work included:
- 2019 work included: Chute Modifications, Deluge Valve House, Washdown Trough, Shiploader Pins, Conveyor Belt Pully, Transformer Drip Tray, Potash Chute Leak Repairs, Bogie Grounding Plates, Hose Rack Handrail, CST Handrail Replacement, Hood Belt Seal Mods, Wind Guard Chute Repairs and Confined Space Entry Assistance.
- 2020 work included: Wind Lock Access Platform, improved Fall Protection at Access Stairs, Enlarge Opening for Ladder Access, Gearbox Pin Removal, Deflector Plate Repairs, Repairs and Modifications to Access Door Panels, Washdown Chute Repairs, and the Hold Down Roller replacement.
- 2021 work included: Transformer Spill Tray Drainage, Shiploader Fire Repairs and Handrail Extensions.