PCT CANOLA EXPANSION

 

Location:

Port Moody, B.C.

 

Client:

Pacific Coast Terminals Co Ltd.

 

Start Date:

March 2014

 

Completion Date:

March 2015

 

Canola Oil Handling Facility Project 

Brymark’s scope of work included:

This project comprises the civil works for the construction of a new Canola Oil Tank Containment Area. This area consists of a 14’ high by 1280’ long reinforced concrete containment wall that encloses three new 120’ diameter Canola Oil storage tanks. The interior of the containment area consists of Rapid Impact Compaction, New Gavels, HDPE Liner System, Storm Drainage, Structural Pipe Supports, and Foundations.