Construction of Air Liquide’s New Nitrogen Plant Phase II
After previously completing Phase 1, one year prior, Brymark was awarded the Phase II mechanical contract.
Brymark’s scope of work included:
- Placement of 4 additional LIN tanks weighing 112 tons each, 7500hp compressor, modules, 85ft high cold box, 43 Tons of structural steel and over 3500 If of pipe for a total of 40,000 manhours. This project was completed with ZERO Recordable and ZERO Lost Time Injuries, ahead of schedule.