+1 604-944-1206

AIR LIQUIDE PHASE II NITROGEN PLANT 

 

Location:

Dawson Creek, B.C.

 

Client:

Air Liquide Canada

 

Completion Date:

October 2013

 

Construction of Air Liquide’s New Nitrogen Plant Phase II

After previously completing Phase 1, one year prior, Brymark was awarded the Phase II mechanical contract.

Brymark’s scope of work included:

  • Placement of 4 additional LIN tanks weighing 112 tons each, 7500hp compressor, modules, 85ft high cold box, 43 Tons of structural steel and over 3500 If of pipe for a total of 40,000 manhours. This project was completed with ZERO Recordable and ZERO Lost Time Injuries, ahead of schedule.